Mimico 180-Unit Lakefront Building-Wide Fan Coil Replacement
A documented project record from Condo HVAC Repair Toronto. A lakefront Mimico building with fan coils well past 25 years had corroded drain pans, failing PSC motors and a reserve fund study that flagged HVAC as the next major capital item. The board approved a phased replacement that kept every resident in their suite.
By The Condo HVAC Repair Toronto Crew
Project Attributes
- Scope
- Building-wide rolling fan coil replacement
- Price
- $186,000 CAD
- Payment
- Progress billing by floor, holdback at commissioning
- Lead time
- 8 weeks equipment procurement
- On site
- 14-week rolling install
- Client
- Condo corporation board
- Crew
- Elena Vargas (Ops Mgr) + 2 crews
- Equipment
- Replacement vertical fan coils with ECM motors
- Neighbourhood
- Mimico
- Building
- 180 suites, 1990s construction
The Challenge
Lake-effect humidity had corroded galvanized pans and cabinet bases faster than inland buildings. Leak calls were up every year and two insurance claims in one season pushed the board to act.
The corporation needed the program to fit a reserve fund cash flow, so the work had to be billed by floor with a holdback until commissioning.
Results
- Building-wide replacement completed inside the 14-week window.
- Progress billing by floor matched the reserve fund draw schedule.
- Leak calls from the original fan coils dropped to zero after completion.
- Commissioning logbook filed for the next reserve fund study update.
How We Ran It
- 1
Spec and procurement
Elena Vargas wrote a like-for-like dimensional spec so new cabinets fit the existing closets and riser connections, with ECM motors for quieter operation. Equipment lead time was 8 weeks.
- 2
Floor-by-floor schedule
The board approved a 14-week rolling calendar posted in every elevator. Each suite was out of service for one working day at most.
- 3
Two crews, one sequence
Crew A drained, removed and disposed of old units. Crew B set, piped, wired and started the new coil the same day. Floor protection and dust control were standard in every suite.
- 4
Commissioning logbook
Each unit was started, checked for leaks and recorded with supply temperature and motor settings. The board received the logbook and warranty certificates at close-out.
Project Photos
Click any photo to enlarge it.
More Condo HVAC Projects
Yorkville Yorkville 42-Unit Tower
Annual Fan Coil Service Program
- Scope
- 42 coil descales + 4 pumps + 11 valves
- On site
- 3 service nights across 2 weeks
- Crew
- Marcus Chen (Ops Mgr) + 4 technicians
- Equipment
- McQuay vertical fan coils, 2001 vintage
- Neighbourhood
- Yorkville
Downtown Markham Downtown Markham 24-Unit Mid-Rise
Water-Source Heat Pump Repair
- Scope
- Reversing valves + contactors
- On site
- 6 days over one season
- Crew
- James Kowalski (Ops Mgr) + 2 technicians
- Equipment
- Trane Axiom water-loop heat pumps
- Neighbourhood
- Downtown Markham
Agincourt Agincourt Low-Rise Magic-Pak
Two-Floor Magic-Pak Replacement
- Scope
- 16 units to MGE series + louvers
- On site
- 8 working days
- Crew
- David Okonkwo (Ops Mgr) + 3 technicians
- Equipment
- Magic-Pak MGE series
- Neighbourhood
- Agincourt
Planning Work Like This in Your Building?
Start with a free walk-through and readings in sample suites. Your board gets a written scope, per-unit pricing and a schedule before anyone commits.
- Written scope before work
- TSSA + Enbridge Red Tag + ESA + WSIB
- Written workmanship warranty