Magic-Pak PTAC Replacement | Agincourt

Agincourt Low-Rise Magic-Pak Two-Floor Replacement

A documented project record from Condo HVAC Repair Toronto. An Agincourt low-rise had original 1990s gas Magic-Pak units on two floors, with compressor failures and one Enbridge Red Tag in the previous winter. The facilities director wanted both floors done at once at bulk pricing.

By The Condo HVAC Repair Toronto Crew

$92,800 CAD 8 working days 16 suites over 2 floors
Technicians lifting a new Magic-Pak MGE unit into a closet in an Agincourt low-rise

Project Attributes

Scope
Replace 16 original 1990s Magic-Pak units with MGE series, new louvers, gas sign-off per suite
Price
$92,800 CAD
Payment
50% deposit, balance at sign-off (bulk 10+ pricing)
Lead time
5 weeks
On site
8 working days
Client
Facilities director, condo corporation
Crew
David Okonkwo (Ops Mgr) + 3 technicians
Equipment
Magic-Pak MGE series
Neighbourhood
Agincourt
Building
16 suites over 2 floors, 1990s construction

The Challenge

The units were original to the building and parts were getting hard to source. One unit had been Red Tagged by Enbridge for a heat exchanger issue, leaving the suite without heat until a replacement was arranged.

Residents needed heat back the same evening, so each suite had to be removed, set, vented, gas-tested and signed off in a single working day.

Results

  • 16 units replaced in 8 working days at bulk 10+ pricing.
  • Every suite had heat back by evening on its install day.
  • Red Tag cleared with code-compliant replacement and paperwork.
  • Old units removed and disposed of by the crew.

How We Ran It

  1. 1

    Site survey and louver check

    David Okonkwo measured every closet opening and louver. The MGE series fit the existing openings, and new louvers were ordered to match the wall sleeve depth.

  2. 2

    Two suites per day

    A crew of three removed the old unit, set the new one, connected gas, venting and condensate, then started and tested it. The gas technician completed sign-off before leaving each suite.

  3. 3

    Red Tag closed out

    The tagged suite was scheduled first so the documentation could be filed and the tag cleared with the new equipment in place.

Project Photos

Click any photo to enlarge it.

"Swapped 16 Magic-Pak units on two floors with gas sign-off done the same day for each suite. Residents had heat back by evening every time."

Rob H., Facilities director, Agincourt

24-Hour Condo Emergency Dispatch

Planning Work Like This in Your Building?

Start with a free walk-through and readings in sample suites. Your board gets a written scope, per-unit pricing and a schedule before anyone commits.

  • Written scope before work
  • TSSA + Enbridge Red Tag + ESA + WSIB
  • Written workmanship warranty
Call (647) 294-5454 Book $185 Diagnostic